Mainteance for Submersible Pump Operation
Mainteance | Installation |
Starting | Connecting & State | Caution & Problem

[ Starting Operation ]
|

|
1. Starting
Operation
|
|
|
- Caution
- Measure voltage and power of the
pump with voltmeter
- Measure Insulation resistance (20M§Ù)
- Clean the inside of Pit and Sump
- Sequence of operation
- Open discharge valve
|
Model
|
JPD JPDL
|
JPW
|
JPH JPHH
|
JPS
|
JPP
|
JPR
|
JPG
|
JPV JPSV
|
JPDU
|
|
Value Switch
|
1/3 Open
|
1/3 Open
|
1/3 Open
|
3/3 Open Full
|
3/3 Open Full
|
3/3 Open Full
|
1/3 Open
|
1/3 Open
|
1/3 Open
|
- No Fuse Breaker is 'ON' and Selector
Switch is 'MANU', then press 'On' button Check
the rotary direction after installation
- When you see from motor side: clockwise
- When you see from the pump side: anti-clockwise
- If the electric current keeps
within the rated current when the pump is operating,
keep it for 1 hours. If there is no any problem
continuously , set Selector Switch on 'AUTO'
|
|
|